Dirección de obra Sagunto II

The Parc Sagunt II Structural Road opens to traffic in Valencia, with the technical support of SOCOTEC Intercontrol.

Thu 24/07/2025 - 11:40

Parc Sagunt II's Structural Road, a crucial access point for the development of this strategic business area, is now open to traffic, thanks to the technical support of SOCOTEC Intercontrol

📷 GVA communication

 

This infrastructure, which will consolidate one of Europe's largest business parks, received technical support from SOCOTEC Intercontrol, a leading engineering firm in the development of major infrastructure projects in the Valencian Community.

Driven by the Generalitat Valenciana and Espais Econòmics Empresarials, and officially inaugurated by the President of the Generalitat, Carlos Mazón, this road is of vital importance for the future PowerCo Gigafactory to be established in Parc Sagunt II.

The project aims to link Parc Sagunt I with Parc Sagunt II and the adjacent Camí la Mar industrial estate, efficiently connecting them with the V-23 and AP-7, as well as facilitating future access to the PowerCo gigafactory.

image background

Engineering for Civil Works

New Structural Road

Dirección de obra Sagunto II

The road, with a length of 2.5 kilometers and two lanes in each direction, includes two major overpasses:

  • A 640-meter section over the CV-309 and the future Sagunto Intermodal Platform.

  • Another 613-meter section that crosses the railway access to the Port of Sagunto.

These elements make the road the backbone of the entire Parc Sagunt II urban development.

Throughout the project's 27-month execution, SOCOTEC Intercontrol's laboratories were responsible for conducting all material control tests, ensuring the highest quality at every construction stage.

The road, with a length of 2.5 kilometers and two lanes in each direction, includes two major overpasses:

  • A 640-meter section over the CV-309 and the future Sagunto Intermodal Platform.

  • Another 613-meter section that crosses the railway access to the Port of Sagunto.

These elements make the road the backbone of the entire Parc Sagunt II urban development.

Throughout the project's 27-month execution, SOCOTEC Intercontrol's laboratories were responsible for conducting all material control tests, ensuring the highest quality at every construction stage.

"This project presented a technical challenge to meet the viaduct's opening deadlines," highlighting the complexity of the work that now connects Parc Sagunt I with Parc Sagunt II and the Camí la Mar industrial estate, significantly improving connectivity with the V-23, the AP-7, and the future access to the gigafactory.”

Pascual Abad

Head of Civil Engineering Department, SOCOTEC Intercontrol

 

This new infrastructure is crucial for the proper integration of the Camp de Morvedre region, ensuring the optimal development and functioning of its industrial fabric.

Furthermore, it solidifies Parc Sagunt's position as a fundamental economic engine, largely thanks to the coordinated efforts of SOCOTEC Intercontrol's civil engineering and quality control teams, who are supporting its transformation into a central hub for economic development, both within the Valencian Community and at a national level.